April
2026

A01 - completed the installation of vertical and horizontal elements of the frame of the 5th floor, completed 67% of the installation of vertical and horizontal elements of the 6th floor; completed 32% of the arrangement of the vertical elements of the 7th floor; completed 86% of the retaining wall; continued backfilling of pit pits - completion 68%.

A02 - completed the installation of the foundation of the house A02; vertical constructions of the basement floor were carried out - completion 16%; performed vertical waterproofing of the foundation of building A02; a complex of water lowering works was carried out.

Parking P02 - the first stage of the development of the pit for the installation of the water lowering system continues - completion 63%