A01 - completed the installation of vertical and horizontal elements of the 7th floor frame, completed 67% of the installation of vertical and horizontal elements of the 8th floor; completed 67% of the installation of vertical elements of the 9th floor; completed the installation of the retaining wall; continued the backfilling of the pit sinuses - 83% completed; mounted window and balcony block samples; completed the tender for the installation of masonry and started the work.