A01 - completed the installation of vertical and horizontal frame elements of the 15th floor; completed 45% of the vertical elements of the 16th floor; performed the installation of masonry - 29% completed; performed the installation of ventilation and smoke protection systems - 14% completed; delivered the first 18 aluminum window structures; began designing a hinged ventilated facade; completed the installation of the 2nd level of ties and the extension of the tower crane.
A02 - completed the installation of monolithic structures of the 4th floor; completed the installation of a retaining wall and light wells; completed insulation and vertical planning of the soil to the design level; completed a complex of works on water lowering.
Parking P02 - a complex of works on water lowering was performed; performed a complex of earthworks to prepare the base for the foundation slab - 50% completed; Work was carried out on the installation of the foundation slab and waterproofing - 25% completed.
Construction site organization - a second diesel power station with a capacity of 550 kW was purchased and installed to provide backup power supply for the construction mechanisms of the II launch complex (building A02 and parking lot P02) during blackouts;
100% of the supply of reinforcing steel for the installation of the parking lot was completed.