September
2026

A01 - finishing of vertical and horizontal elements of the frame on the 13th and 14th surfaces has been completed; viconals 45% of vertical elements 15th from the top; vykonuvali vashtuvannya stone masonry - vykonannya 22%; installation of ventilation and anti-inflammatory systems was carried out - 6%; the production of aluminum windows has begun; They identified a suspended ventilated façade and internal heating systems, water supply and water supply.

A02 - finishing of monolithic structures of the 3rd from the top has been completed; the finishing of the pressure wall and light pits was done - 87%; The complex works on water reduction.

Parking P02 - installed robotic complex with water reduction; The famous Vikonavian earthworks, reinforced concrete frame and waterproofing.

Organization of the alarm system - KTP-2 is switched on to ensure the electrical supply of the alarm mechanisms of the booths of the 3rd launch complex (bodies A03-A04);

the delivery of 100% reinforcement bars for budinki A01-A02 has been completed; the supply of reinforcement bars for the parking lot was ordered - 3 cars were delivered; a surplus of ceramic block and mineral wool insulation for the A01 cabin was accepted

September
2026