A01 - completed the installation of vertical and horizontal elements of the 3rd floor frame, completed 67% of the installation of vertical and horizontal elements of the 4th floor; completed 67% of the installation of vertical and horizontal elements of the 5th floor; completed 62% of the retaining wall; continued to backfill the pit sinuses - 53% completed.
A02 - completed the installation of the soil base and concrete preparation for the installation of the foundation of the A02 building; completed the installation of the tower crane foundation; completed horizontal waterproofing of the A02 building foundation; completed waterproofing and concreting of elevator pits; performed reinforcement of the A02 building foundation - 40% completed; performed a complex of water reduction works.
Parking P02 - completed additional geological exploration wells; The first stage of development of the excavation for the installation of a water lowering system has begun - 12% completion