June
2026

A01

  • Continued installation of utility service entries and light wells;

  • Continued installation of the lightning protection system;

  • Continued construction of the reinforced concrete structural frame, reaching 70% completion of the vertical elements and 70% completion of the 9th-floor slab;

  • Continued installation of the vertical waterproofing system for the underground structure;

  • Continued backfilling of the excavation pit;

  • Commenced construction of the external and internal masonry walls.

A02

  • Continued construction of the reinforced concrete frame of the basement level;

  • Continued installation of the vertical waterproofing system for the underground walls;

  • Continued installation of the drainage membrane;

  • Continued backfilling of the excavation pit;

  • Continued groundwater dewatering works.

Parking Structure P02

  • Continued excavation works for the underground parking structure;

  • Completed installation of the test bored injection piles for test pile groups No. 1 and No. 2;

  • Completed load testing of the test piles in accordance with the approved testing program.

Off-site Works

  • Continued installation of external utility networks, including underground electrical cable installation;

  • Completed installation and commissioning of Transformer Substation No. 2 (KTP No. 2).

June
2026