A01
Continued installation of utility service entries and light wells;
Continued installation of the lightning protection system;
Continued construction of the reinforced concrete structural frame, reaching 70% completion of the vertical elements and 70% completion of the 9th-floor slab;
Continued installation of the vertical waterproofing system for the underground structure;
Continued backfilling of the excavation pit;
Commenced construction of the external and internal masonry walls.
A02
Continued construction of the reinforced concrete frame of the basement level;
Continued installation of the vertical waterproofing system for the underground walls;
Continued installation of the drainage membrane;
Continued backfilling of the excavation pit;
Continued groundwater dewatering works.
Parking Structure P02
Continued excavation works for the underground parking structure;
Completed installation of the test bored injection piles for test pile groups No. 1 and No. 2;
Completed load testing of the test piles in accordance with the approved testing program.
Off-site Works
Continued installation of external utility networks, including underground electrical cable installation;
Completed installation and commissioning of Transformer Substation No. 2 (KTP No. 2).